This is a construction timeline of our new home.  It begins with the purchase of the lot all the way up to and including moving day!  Click on the thumbnail photos below for a larger picture.

Click HERE for an itemized timeline in Excel format.

     
November 9, 2002 11-09-02.jpg (88436 bytes) Moving Day finally arrives!!!  Thanks to the help of 15 people, we were done by noon moving both the apartment and the storage unit!  Special thanks to Jeremy Pell for helping prep the full day before.
October 28, 2002 10-28-02.jpg (73022 bytes) The kitchen countertops were installed today.  Plumbing is also now complete.
October 27, 2002 10-27-02a.jpg (35277 bytes)

10-27-02b.jpg (43225 bytes)

It's hard to see, but the landscape lighting is done and turned on for the first time.  We also spent the day doing yard work  - 1 1/2 hours of straight mowing time :( 
October 4, 2002 10-04-02a.jpg (53999 bytes)

10-04-02b.jpg (49607 bytes)

Interior painting continues along with ceramic tile installation.
September 28, 2002 9-28-02a.jpg (115950 bytes)

9-28-02b.jpg (66237 bytes)

9-28-02c.jpg (115382 bytes)

9-28-02d.jpg (58113 bytes)

Landscaping is under way.  Marty (the landscaper) is seen installing the plant beds, mulch, and accent lighting.  Concrete curbing and sod is scheduled for next week.
September 27, 2002 9-27-02.jpg (47187 bytes) The lawn irrigation system was installed today.  The entire system was in place and working by sunset!
September 24, 2002 9-24-02a.jpg (40538 bytes)

9-24-02b.jpg (51095 bytes)

Interior work continues with the application of paint and sub-flooring.  All trim work is nearly complete with the exception of kitchen cabinetry.  The cabinets are still being custom-built at the factory and are due in at any time.  The downspout drains were installed today and finish-grade begun on the outside.
September 4, 2002 9-4-02a.jpg (59691 bytes)

9-4-02b.jpg (65931 bytes)

Sidewalk and driveway work begins today with the application of forms.  McKinley Foster (a.k.a. "The Best Concrete Man in the Business") can be seen in the top photo in the back of the truck.
September 2, 2002 9-2-02.jpg (35656 bytes) Drywall work is now complete with crews finishing the ceiling texturing and sanding.
August 14, 2002

8-14-02a.jpg (363245 bytes)

8-14-02b.jpg (580838 bytes)

Drywall is underway on the inside and gutter application has begun outside.
August 12, 2002

8-12-02a.jpg (389421 bytes)

8-12-02b.jpg (568681 bytes)

8-12-02c.jpg (533116 bytes)

8-12-02d.jpg (749696 bytes)

Brick is complete (or at least 99%).  Still a couple of final touches to be done including the address block below.

August 10, 2002

8-10-02a.jpg (187428 bytes)

8-10-02b.jpg (556021 bytes)

Insulation is complete.  Downstairs we installed traditional batt-style insulation, but upstairs we used a blown-in type.  The blown-in type supposedly provides a far superior barrier.

August 2, 2002

8-2-02a.jpg (57210 bytes)

8-2-02b.jpg (83980 bytes)

Bricklayers continue their work (day 3).  The bottom photo shows a close-up of the brick color by the front stoop.  Also seen is the 'year built' block.

August 1, 2002

8-1-02a.jpg (78730 bytes)

8-1-02b.jpg (62609 bytes)

Whew! The wiring is done! I finished the phone, cable, cat5e (computer), two home theaters, and the security system today.  After running a couple of miles (literally) of wire to 52 points of termination around the house, I'm ready for a vacation.  Thanks to Mark Culver, Candy Ashby, and Rob Skiver for helping out.
July 31, 2002 7-31-02.jpg (56726 bytes) The bricklayers finally show up and begin to work.  In this photo they are just setting up.

July 29, 2002

7-29-02a.jpg (69268 bytes)

7-29-02b.jpg (54320 bytes)

7-29-02c.jpg (49165 bytes)

7-29-02d.jpg (46554 bytes)

7-29-02e.jpg (49680 bytes)

OUCH!

Heavy rains and high winds cause a retaining wall on one of the window wells to collapse inward into the basement wall.  Damage was minor and will be repaired by the end of this week.  The same storm also ripped several large sections of shingle caps.

July 14, 2002

7-14-02a.jpg (53382 bytes)

7-14-02b.jpg (61294 bytes)

7-14-02c.jpg (79901 bytes)

Top picture shows view from living room showing dining room and entry.  Our new address is shown on the permit (3725 Highland Park Drive) and an arsonist strikes our dumpster on July 13 at 1:13 in the morning.  No damage to the house.

July 12, 2002

7-12-02a.jpg (60274 bytes)

7-12-02b.jpg (76450 bytes)

Windows and exterior doors are installed.  Shingles started and base coat of paint applied to exterior trim.

July 4, 2002

7-4-02a.jpg (48792 bytes)

7-4-02b.jpg (46858 bytes)

7-4-02c.jpg (44918 bytes)

7-4-02d.jpg (43059 bytes)

Most framing is complete.  Exterior trim has begun along with door and window installations.

June 26, 2002

6-26-02a.jpg (55633 bytes)

6-26-02b.jpg (68401 bytes)

6-26-02c.jpg (67703 bytes)

6-26-02d.jpg (590713 bytes)

Roof framing complete. Decking started before more heavy rain halts work for the day.

June 25, 2002

6-25-02a.jpg (94647 bytes)

6-25-02b.jpg (68553 bytes)

6-25-02c.jpg (51418 bytes)

Proof that wood floats! Heavy rains slow progress as the basement becomes a pond and keeps the sump pump working overtime.

June 21, 2002

6-21-02a.jpg (58930 bytes)

6-21-02b.jpg (50883 bytes)

6-21-02c.jpg (67256 bytes)

6-21-02d.jpg (74704 bytes)

Roof framing under way.

June 13, 2002

6-13-02.jpg (514446 bytes)

Main floor framing complete.

June 7, 2002

6-7-02.jpg (562859 bytes)

Framing begins in basement.

June 3, 2002

6-3-02.jpg (424685 bytes)

Back-filling begins.

May 30, 2002

5-30-02a.jpg (573670 bytes)

5-30-02b.jpg (624736 bytes)

Basement foundation is complete.

May 21, 2002

5-21-02.jpg (577243 bytes)

Basement walls are poured.

May 16, 2002

5-16-02.jpg (648638 bytes)

Basement is dug and footers are poured.

May 1, 2002

5-1-02.jpg (430993 bytes)

Newly purchased lot in Highland Park.  The lot is later staked on May 5, 2002

    