White River Township Fire Protection
District
Board Meeting Minutes
March
6, 2007
District Board Members Present:
Dr. Chuck Shufflebarger
Rev. Jim Dodson
Butch Sutton
Jon Raker
Paul Kite
Chief
Cassin
Chief
Brown
Chief
Thacker
Chief
Slauter
Chief
Engmark
Captain
Hart
Captain
Arkins
Lt.
J. Smith
Lt.
Hurrle
Lt.
Green
Crystal
Young
Others Present:
Tricia Leminger
Steve Dyson
Dudley
Senefeld
Scott
Senefeld
Dan Sulkoske
Note: Motions
are italicized and in blue.
Dr. Shufflebarger called the meeting to order at 7:05
p.m.
I.
Approval of Minutes from February 6th
Meeting
a. Jon
Raker motions that the minutes be approved.
Butch Sutton seconds.
b. All
in favor and motion carries.
II.
Financial Update
a. Chief Cassin stated that the bank balance is on pg.
10.
b. Page 11 lists all funds. Chief Cassin stressed that several are
currently running under budget and that he did not list each fund individually
since he has sent several e-mails to board members who had questions over
specific funds.
c. Page 14 is the statement of Capital Outlays.
i.
The Thermal
Imaging Camera has been purchased and is complete.
ii.
The EMS Monitors
have been purchased.
iii.
Turnout gear
replacement for 2007 has begun.
d. Page 15 is an overview of the Station 51 Construction
Project. At this point little over half
of the funds have been spent.
III.
Old Business
a. Station 51 Building Project Update
i.
Scott Senefeld
stated that things are progressing slowly.
ii.
Ms. Leminger believes
that the board worked through the work orders during the last meeting.
iii.
Those change
orders were covered and issues were presented during the last progress meeting
and they have been readied for signatures.
1.
At this
point Dan Sulkoske and Scott Senefeld stated that the contractors have
submitted delay days to the change orders.
Both suggest scratching out the days on the change order and deal with
each individual day. They have requested
that Steelcorp submit a list as to what the delays are related to.
2.
Mr. Sulkoske
stated that he had received a delay letter from Steelcorp a couple of weeks ago
but he has just gotten the letter to Ms. Leminger. The bulk of the delays stated in the letter
are weather related and drainage related.
They have been waiting on
a.
To
reiterate,
b.
Attempts to
get
3.
The next
issue is with Bargersville Utilities.
Senefeld went through the proper channels, submitted the drawing to the
correct officials and the project was a go.
Mr. Sulkoske distributed a drawing of the property and the location of
the water line and pavement in question to the board.
a.
The blue
line represents the 12 inch water line they want us to move; the pink line is
the adjacent property line (as built drawing).
b.
Asphalt was
then added to
c.
The issue is
why weren’t they made to move the water line when they crossed over our
property line. We do not believe we
should have to pay for that but we cannot get the proper approval and
connection until it has been moved.
d.
Drawings
were submitted on what was there; we have not added any asphalt nor plan
to. These drawings were approved by TAC,
the city and
i.
Senefeld has had
this issue with the same utility on another project. He has brought a copy of all transmittals for
the board to review. In this situation
we are not paving over the utility but their interpretation of the situation is
different.
ii.
They are forcing
us to improve their utility at our expense and putting us between a rock and a
hard place. If we do not make the
improvements we cannot hook into the utility.
e.
At one point
there was a rough grade then stone and was then paved late in the project. No one is sure at this time if plans had
changed or who made the change but the deceleration lane continues from the
property to the east all the way to Herron Ridge.
i.
Mr. Sutton
inquired as to who the developer was to the east to which Chief Brown stated
Capital Construction and Williams Reality and to this point they have had
several problems with the strip mall.
f.
Mr. Raker
asked if anyone has spoken or been in contact with the developers concerning
this topic.
i.
There have been
discussions but they are not volunteering any action. In this case Bargersville has lost their
bargaining chip with the adjacent property; they can no longer do to that
project what they are doing to this project because they have already hooked
into the utility. Even if it is
successful it is still in there hands as to the schedule of when the job will
be complete.
g.
Several
meetings have been set up with Bargersville and several where no one showed
up. They are firm in their position that
the line needs to be moved before we can tap into it, it does not matter
whether we do it or the developer to the east.
h.
Ms. Leminger
asked if they are firm on whose responsibility this would fall under, to which
Chief Brown replied that it is the responsibility of the one who makes the
improvements.
i.
Dr.
Shufflebarger inquired as to how they were able to pave over this section of
our property. Chief Brown responded with
the fact that it is paved in the right away.
Dr. Shufflebarger stated that by using the easement or right away
shouldn’t they be responsible in making the necessary changes.
i.
Mr. Sulkoske
stated that that is what everyone believes.
Dr. Shufflebarger stated that no matter who is at fault, at this point
we need to get hooked in while we are finding out who is at fault. Should we go ahead with the drawing, move the
line then decide who is at fault and who we can go after for the expense.
ii.
Mr. Raker stated
that maybe we ought to get it moved then work on reimbursement.
iii.
Ms. Leminger
stated that at this point the estimates are all over the board, first estimates
were around 20 and now it is up to 60.
Mr. Sulkoske stated that there are a number of different issues that
have been sketched out that will need to be taken to Bargersville Utilities for
their approval before and estimate from the contractors can be obtained.
i.
Bargersville
told Senefeld that there will need to be a whole new redesign and Mr. Senefeld
stated that it would be ludicrous until we know what they want so a sketch was
drawn up and will need to be reviewed by Bargersville Utilities for their
requirements. The intent was to show
this drawing to Bill Reynolds during the last progress meeting but he did not show
up. Mr. Reynolds was contacted and
stated that he was not going to do anything until he was paid his $1000 review
fee. He did show up on site last Friday
and met with reps from Steelcorp and Kramer and that is where the sketch
originated.
ii.
From this step
it can be put into a hard line drawing.
Once that occurs it will have to be approved which could take up to six
weeks. All the prep work leading up to
the connection can be done.
j.
Mr. Sulkoske
stated that Dr. Shufflebarger is right in the opinion that they did the
improvement they should have moved the line.
Mr. Raker stated that he did not understand why Bargersville Utilities
didn’t make them move it at that original time, why would they approve the
small section without fixing the whole thing.
Chief Brown stated that typically the people doing the improvements are
the ones responsible. Mr. Sutton stated
that we should go to Bargersville Utilities and threaten to sue or have them
turn off the water to the adjacent property.
k.
Chief Brown believes that we should first get
the requirements from the county; he will be able to pull from the file
tomorrow.
l.
Ms. Leminger
inquired on the impact on the project due to this issue.
m. Mr. Sulkoske stated that there are a host of other
issues that need to be discussed. Kramer
is suggesting that the board scratch the delay days and discuss each day
separate and negotiate with the contractor. The board should ask for a written submission
and description of why. Dan and Scott
agree to proceed to change order. Ms.
Leminger asked if these were the change orders discussed in the last meeting
and was affirmed. Along with the change
orders they are asking for (X) amount of days to make the changes.
i.
Once approved
the change orders would need to be re-issued for re-circulation, Mr. Sulkoske
agreed and stated that he could get them initialed tomorrow but that their main
concern is the change orders not the delays.
There were production issues that are off setting some of the site
issues.
ii.
There are some
legitimate production issues, one of them being the weather another being
4.
The next
issue is the Dual Sump Pump issue that was not originally agreed on by the
board.
a.
There has
been a water event in the basement. Mr. Sulkoske
stated that the situation may improve when the hard scape goes in but it may
not. This system would be like an
insurance policy. The current system can
handle it but there have been problems there, it all hinges on how confident
the board is in the current system and would like for the board to consider it
again.
5.
Dr.
Shufflebarger would like to get an inventory of the issues that need to be
taken care of today.
a.
The utility
issue is the biggest issue on the table right now. Should we look into the adjacent
property? Ms. Leminger has not reviewed
the guidelines and is unable to give a recommendation at this time. Mr. Senefeld will get the drawing in hard
copy and speak with the utility to get pricing.
b.
Mr. Kite
inquired as to what was needed from the board in the next 30 days to get things
going. The board will not need to do
anything and it can sit idle until more information from the utility and a firm
cost is figured.
c.
Dr.
Shufflebarger stated that we need to do what is needed to get the approval
process going so we can get hooked up to the utility and would like to have all
the behind the scenes process taken care of by the next meeting. Mr. Senefeld believes it can be resolved by
the next meeting as long as they can set up a meeting with Bargersville
Utility.
6.
Other items
have already been approved they just need to have the days scratch from them
and initialed.
7.
The issue of
the sump pump was re-addressed and the cost of the project was requested. The cost would be $8650; Dr. Shufflebarger asked
if any board member has any feelings on the issue.
a.
Mr. Raker
had a flooded basement a week ago and placed a dual sump pump in his own
basement so he is in favor of the system.
b.
Chief Cassin
stated that last week we had a problem with a frozen line and it caused water
to back up into the basement. He feels
it is worth the expense. No one spoke
out against the idea.
8.
Paul Kite motions to accept the dual sump
pump. Jon Raker seconds.
9.
All in favor and motion carries.
iv.
Dr.
Shufflebarger asked if there is a revised schedule and when the delivery date
may be. Mr. Sulkoske believes the
delivery date will be near the end of June.
1.
Mr. Kite
asked if Senefeld is in agreement with Kramer on the delivery.
2.
Mr. Senefeld
concurs and stated that the schedule is going to be crunched up near the
end. The first change order will add 90
days. He also believes the delivery date
is far off enough to not give a specific date and hopes it will not take that
long.
3.
Also JE
Mechanical will need to proceed to install the electric. The water will need to go in around that once
the issue is resolved.
4.
Mr. Sulkoske
stated that another issue being dealt with at this time is the drywall in the
basement. The installers were waiting on
the decision on the pump and a drier basement.
Kramer will need to address every contractor per process.
v.
Mr. Senefeld
also stated that with the change orders in place contractors will be able to
revise the schedule. Several of them are
stating that there is revised engineering that needs to be done but that is not
what is occurring. Revised coordination
is what will take place. Kramer and
Senefeld will talk to each contractor, address the issues and revise the
schedule during each progress meeting.
1.
JE Mechanical
has gone through an employee change. Their
work has slowed during this process but they will respond to that in written
form and near the end of the project all these situations will be reviewed.
vi.
Ms. Leminger
wanted to make an amendment to last months minutes concerning the total of
change order 1. She had stated the total
to be $12522 but it is actually $13259.
vii.
Mr. Senefeld
stated that he did not want to panic anyone; there are several issues that are
being worked through. Obviously the
biggest issue is the problem with the water utility but everything is continuing
inside the building.
viii.
Mr. Sutton
wanted to know who is doing what with the water issue.
1.
Mr. Sulkoske
stated that Senefeld will complete a hard line copy verify the drawing with
Bargersville and proceed with a new design.
At the same time find out why the adjacent contractor did not have to move
the water line.
2.
Chief Brown
stated that we need to determine what the true requirements are, who installed
the excel lane and find out who may be responsible.
3.
Mr. Senefeld
stated that the general rule is if you pave over a utility you have to move it.
4.
Dr.
Shufflebarger inquired as to whether we were going to do similar paving. Mr. Senefeld’s answer was no, the original
drawing was set to the existing pavement.
5.
Senefeld
received a letter from Tec review stating that changes need to be made to our
plans to show the neighbors excel/decel lane.
The only real change is that the front yard got shorter.
6.
Dr. Shufflebarger
asked if this lane had to be there and Chief Brown’s response is that the lane
is required.
7.
Chief Brown
asked why we couldn’t tap our line off of the adjoining property. He will pull the documents from the court
house tomorrow to get a better idea of what is going on.
ix.
Dr.
Shufflebarger stated that in the mean time the decision is to do the drawings,
meet with Bargersville Utilities, get an estimate then once there is a
reasonable answer sit down with Ms. Leminger and discuss the options.
b. Fire Chief hiring process update
i.
During the last
meeting the board decided to form a committee to develop a process for hiring a
new fire chief. Mr. Dodson and Mr. Kite
have been working on that with representatives of the department.
1.
Chief
Tibbetts recommended Chief Engmark, Lt Hurrle and firefighter Fletcher to be on
the committee.
ii.
Mr. Dodson
stated that he has handed to the members of the board a copy of the committee
report and a copy of the Fire Chief Job description.
iii.
Mr. Dodson
requests that the board take no action tonight.
He requested that everyone look over the report and the job description
and come prepared for the next meeting with any other recommendations or
updates to either document. He also
asked council to review the process and make sure they are okay with everything
and establish a timetable.
iv.
Additional piece
of information from Mr. Dodson is how other departments have advertised for the
position.
v.
Dr. Shufflebarger
then stated that the board should come prepared to finalize the job description
and timeline for the process.
IV.
New Business
a.
i.
Mr. Dyson asked
Chief Cassin if he has heard from
ii.
There was an
article today that they will not get the bills out on time.
iii.
Mr. Dyson stated
that the delay will not affect on cash flow.
He did want to inform Chief Cassin that he will not receive the 1782
until all assessments are done.
iv.
There will not
be a huge delay in this process.
V.
Adjournment
a. Meeting adjourned at 8:07 by Dr. Shufflebarger.
Next meeting will be April 3, 2007 at 7 p.m.