White River Township Fire Protection
District
Pre-Meeting
Report for August 1, 2006
Compiled July 27, 2006
- Due to the proximity of the end of the month to
the board meeting date, month-end financial reports will not be available
prior to the meeting. We will make
every attempt to have the reports completed in time for the 7pm meeting commencement
on August 1st.
- The State Board of Accounts has begun their
audit of the Fire Protection District.
They are auditing 2002, 2003, 2004, and 2005. Typically these are done every two years, however they have gotten way behind and now have
a goal to get everyone caught up by the end of the year. We have been working with them over the
past two weeks obtaining records and other items needed. We have established a great working
relationship with the two auditors and have gained invaluable information
and insight during the process so far.
Because the State Board of Accounts is so far behind, the auditors
are working a lot of overtime. The
two auditors assigned to our case have since been pulled to go to Ivy Tech
to begin their audit (which takes nine months to complete!) So, according to their supervisor, it
may be several more months before ours is completed. Once competed however, they will meet
with the Chief, me, and at least one board member for an exit interview.
- No new news on the Task Force One agreement at this
time. Per request of the board at
last month’s meeting, the topic will not be included on the agenda unless
new details become available before the next meeting.
- The pre-build meeting with Towers Fire Apparatus
took place last week regarding the replacement of Engine 54. The two-and-a-half hour meeting went
extremely well and everything is now set for construction to begin. No delays or problems are anticipated or
expected at this time.
- The Station 52 project is still moving along as
planned and continues to remain on budget.
The ceiling grid was installed and interior finish work has
commenced. Floor tile was being
installed yesterday. We have however
received another complaint from the neighbors (to the south) regarding the
condition of the exterior landscape.
The architects have been in contact with the contractor who has
been given a directive to begin exterior clean-up and landscaping as soon
as possible. As soon as this work
gets under way, we will begin work to restore the southwest corner of the
property to its original or better condition. Currently, there are trees, underbrush,
and other debris that has accumulated in that area over the years and is
in need of attention. Most of the
labor and equipment will be donated to complete this portion of the
project.
- The Station 51 project is still moving along on
schedule as well. Basement backfill
is currently underway and all footings are now in place. The next on-site progress meeting is
scheduled for next Wednesday, August 2nd at 10:30am. Senefeld and Associates will be on hand
at the meeting for a more detailed update.
- Recall that this meeting will serve as the
official approval meeting for the 2007 budget.
- The department is continuing to work with a
local real estate agent on the northwest district property. There currently is one sale in progress
in the development identified last month as the most ideal location. As soon as the sale completes we will
bring that information back to the board.
In the meantime, we are attempting to gather other comparables in
the same general area for further review.
No discussion at the meeting is anticipated or requested at this
time.
- As in years past, the department has held back
on major capital outlays until the second half of the fiscal year in case
of a substantial unexpected expense that would require cancellation of any
one project. This year, in addition
to the planned capital outlays, the department is anticipating some
additional un-budgeted projects.
These projects vary from ones already approved by the board up to
and including wish-list items that have come up since the end of last
year. A recap of these projects is
included below that currently totals $663,613.00. This list is included here just to make
the board aware of these projects.
No discussion is anticipated at this time.
- 2003 and 2004 audit of the former volunteer
corporation - $10,000
- Unpaid bill from former volunteer corporation
for Booster Club mailings - $9,000
- Additional capital required above the 2003 Fire
Loan amount for the Station 52 project - $76,393
- Station 52 workshop area cut from the original
room addition project - $4,900
- Additional mini barn for Strawberry Festival
storage and screen wall repair at Station 53 - $8,000
- Station 53 sewer connection - $100,000
- Additional capital required above the 2005 Fire
Loan amount for the Station 51 project - $350,000
- Fire sprinkler system for the Station 52 room
addition project - $9,000
- Garage structure for small vehicles and
trailers at Station 53 - $85,000
- Quantitative SCBA mask fit testing unit -
$10,000
- Garrison Flag for honor guard unit - $1,320
- That’s all for this month. See everyone at the meeting.
The next meeting is
scheduled for Tuesday, September 5th, 2006.
- Scott