White River Township Fire Protection District

 

Pre-Meeting Report for August 4, 2005

 

Compiled July 25, 2005

 

 

 

1)     We finally received a detailed cost estimate for the Station 52 project from Senefeld and Associates.  It came in at $175,875.  This cost was derived from actual proposals from two separate general contractors, so it should be on target.  The original project, as it was developed almost three years ago, called for a simple room addition for a weight room.  This was the project (based on a simple cost-per-square-foot basis) that was used to derive the $125,000 project cost for the 2003 Fire Loan.  Since then, the project has evolved a bit to include a small classroom and a restroom.  The weight room was also enlarged to include some of the additional equipment that has been added over the last three years.  This, coupled with dramatically increasing construction costs, has led to the overall cost increase of $50K.  Now because the total project is over $150K, we would have to do a common construction wage hearing to continue with the project.  Tricia Leminger was working with President Shufflebarger on how to proceed until the full board can meet to discuss the proposal.  As far as the additional $50K, this amount could be appropriated from the $314K in the “Miscellaneous” category of the Capital Outlay budget of the General Fund, which is currently not targeted for any projects.

 

2)     The Station 51 Building Team met once again with the architects last week to get everyone back up to speed and to make any final changes to the overall layout before the project goes to engineering.  Provided there is no remonstrance and the Fire Loan goes through as planned, the design and development phase should be completed about the same time as the closing of the loan.  This would mean construction could start sometime in October.

 

3)     Because of a communications error, the Fire Protection Ordinance proposal was NOT officially delivered to the County Commissioners in May as previously stated.  However it WAS physically placed on the agenda for this month and a fortified discussion was held at the meeting.  The board of Commissioners seemed favorable toward the idea but instructed the major departments in the county (White River, Greenwood, Bargersville, and Franklin) to get with the Builder’s Association to get their feedback.  The group is then to report back to the Commissioners next month.

 

4)     The benefits sub-committee is still working on the two remaining policy change proposals introduced in May, but we will leave it on the agenda in case there is an update.  To summarize, they are:

 

1.      Change the bereavement leave from one automatic day to two with a possibility of a third granted by the fire chief if the funeral is out of state or other extenuating circumstances occur.

2.      Combine the Personal Leave and the Perfect Attendance Days together and add them as additional vacation days instead.  This would eliminate the need for tracking these additional days.

 

5)     Captain Settles has been working on various projects throughout this year cycling some of the capital equipment on Rescue 51 as per the rotation schedule.  Due up this year (among other items) are replacement air bags.  He has received three quotes which are listed below.  This project is part of his budgeted Capital Outlays under “Equipment” in the General Fund.  He is requesting that the board award the project to Fire Service, Inc for $11,886.  A copy of each of the quotes are attached to this PMR.

 

1.      Fire Service, Inc - $11,886

2.      Hoosier Fire Equipment, Inc - $12,406

3.      RPM, Inc - $12,653

 

6)     As you may recall, in year’s past we have put together an un-appropriated project list containing items and/or projects that weren’t originally budgeted.  These items are then prioritized and funded with either under-budget or un-appropriated funds on a per-item approval basis.  As the year goes on, I keep a list of these requests (sort of a wish list) as they come in and compile them toward the end of the year.  I thought I would share this list with you now as it stands.  (They are in order of submittal and have not been discussed by the Senior Staff as to their necessity)  The project cost estimate is included with each item.

 

1.      $13,000 – Mast camera and control for TSU for incident recording.

2.      $6,000 – ID card printer for ID cards (in lieu of utilizing Greenwood City Human Resources).

3.      $2,000 – Additional computer for officer staff at Station 53.

4.      $50,000 – Additional appropriation for Station 52 room addition project.

5.      $12,000 – AED Pro (x4) to serve as backup monitor/defibrillators on all primary apparatus.

6.      $6,000 – Safety Trailer grant contribution (our portion of the grant).

7.      $10,000 – Audit for 2003 and 2004 Volunteer Corporation (approved amount at the June, 2005 FPDB meeting).

8.      $6,000 – Conversion kits for all M-Series monitor/defibrillators to allow 12-lead ECG’s to be sent via fax to the hospital.

9.      $85,000 – Small garage/structure to house all non-take home vehicles and trailers currently parked outside at HQ.

10. $1,000 – Personnel photo board utilizing professional photography for display at HQ.

11. $18,000 – Thermal Imaging cameras (x2) to be placed on the remaining primary apparatus.

 

Total:  $209,000

 

 

7)     The Aerial (now named Ladder 53), is back in full service following its return from Pennsylvania after the warranty paint repair.  FYI only.

 

8)     The financial reports for the August meeting will be sent out under a different e-mail cover on or around August 2nd (or as soon as the July books are closed out.)

 

9)     That’s it for this month.  See you at the meeting…… Scott