White River Township Fire Protection District
**** Pre-Meeting Report for June 4, 2003 ****
Compiled June 2, 2003
- Station
52 repairs update.
- All
repair work, with the exception of the brick toning, has been
completed. This includes
landscaping.
- We
are still awaiting a final written report from Don Courteau.
- Station
53 septic issues.
- Our
waste removal company has informed us that our drip system has possibly
been installed improperly.
- Water
is currently running into the tank from the field system. This should actually be occurring the
opposite way. This is resulting in our tanks filling and staying
filled. They need to be emptied
2-3 times per month instead of 3-4 times per year.
- Chief
Brown is working with Earthek to get this resolved.
- Policy
manual update.
- Still
in the process of being updated.
- We
are approximately 75% complete.
- Policies
will be posted to the Internet when finalized, possibly as early as the
last week of June.
- Tactical
unit update.
- Committee
still working on project.
- Original
specifications review resulted in costs for the truck being higher than
originally anticipated. The
committee is re-evaluating the spec to find anything that could reduce
the project cost.
- Current
financial update.
- 2003
Fire Loan
1)
Chief Tibbetts has been working on different options for our
2003 fire loan. Included in this would
be land acquisition for future fire stations.
He is currently getting prices for land at various locations throughout
our district.
2)
Other potential projects include building renovations,
extrication tool replacement, and computer system (our current one is 3 years
old and now out of warranty).
- ‘04
Budget update.
1)
As this is being written, budget numbers from our department
heads are still coming in. We hope to
have a preliminary budget for review at the June district meeting.
- Current
financial issues.
1)
We are now paying bills twice per month, on the 10th
and 25th. We had tried to
work these bill paying dates around District board meeting dates in the past,
but found that it was not working because of payment overlaps and past due
invoices.
- So
that we could better answer questions regarding our five year plan, the
Chief officers and other department heads conducted an all-day strategic
planning retreat last week. The
event was very productive as several issues were discussed, including staffing,
station locations, response times, and improving current operations within
several divisions. This is an
ongoing process that will take several months to complete, at which time
we would like to meet with all members of the District Board to review and
finalize the plan.
- The minutes
from the May District meeting are available for viewing on our website, or
by following this link:
http://www.wrtfd.org/downloads/minutes/fpdb/2003/0507.htm
- The
June newsletter is available for viewing on our website, or by following
this link:
http://www.wrtfd.org/downloads/newsletters/Jun03news.doc
CURRENT PROJECTS
Chief Tibbetts
|
* 2003 fire loan.
|
Chief Cassin
|
* Policy updates.
* Overseeing
development of five-year strategic plan.
|
Tactical Committee
|
* Looking for ways
to reduce project costs.
|